all projects

Boiler house pump control distribution

Client

Pirtel

Project date

27. August, 2020

1st round of boiler house reconstruction in a village of Slampe

Tasks

  • Protection and manual control of new mains and feed pumps
  • Old mains pump protection and manual control
  • Feed tank level control and filling
  • Preparation of status signals for the 2nd round of the project

Solutions

  • Installed protection and switching devices (Schneider Electric)
  • Installed control and indication devices (Schneider Electric)
  • Installed relays (Schrack) to provide status signals

Benefits

  • Possibility to operate boiler house pumps during the project transition period
  • Possibility to use the created system for the realization of the 2nd round tasks of the project